Key Road Projects

*All projects are subject to change

Current Projects

Oak Street Sewer Project

All pipe installation is complete and final pump testing is being performed. Surface restoration is complete and any remaining problem spots will be repaired as needed. Final punch list items are being addressed and the system is expected to be operational by the end of May 2022.

Sewer Extension Project

Click here for information about the Sewer Extension project.

Starkey Avenue Closure

Starkey Avenue from the bridge at the Rail Trail to Ford Road will be closed from June 15 - 24 (weather dependent) for a culvert replacement. Local traffic only.

Templin Road Bridge Reconstruction (Boone County Highway Department project)

The shoulder of this bridge is currently closed and work on utility relocation is underway. Construction is estimated to start in the summer of 2022 and be completed in the fall/winter of 2022. Templin Road will be closed during construction with a detour route posted.

US 421 Repaving (INDOT project)

INDOT will resurface US 421 from north of Greenfield Road to SR 32. The contractor will be flagging motorists around the area they will be working. Dates TBD.

CR 300 S. Corridor Project

Through a grant from the Indianapolis Metropolitan Planning Organization, the Town has partnered with the Boone County Highway Department to conduct a corridor study along CR 300 S. from CR 800 E. to the Boone/Hamilton county line. The purpose of this study is to identify a preliminary scope and a potential design of future road widening and intersection improvements considering feasibility, costs, impacts to properties, environmental concerns and bridge needs. 

While there is one known bridge replacement project planned within the next four years, there are no identified intersection or road projects at this time. The information learned from this study will initially guide bridge design as these structures are maintained and replaced as needed. Future intersection or roadway capacity projects will not be undertaken until the volume of vehicles and levels of service justify the improvements.

CR 300 South Concept Plan Section 1

CR 300 South Concept Plan Section 2

CR 300 South Concept Plan Section 3

CR 300 South Concept Plan Section 4

CR 300 South Roundabout Option at CR 875 East

CR 300 South Roundabout Option at CR 975 East

CR 300 South Public Info Meeting Handouts

CR 300 South Public Info Meeting Power Point Presentation

CR 300 South Typical Cross Sections


Projects for the Future

CR 800 E. and Oak St. Roundabout

The Town is completing engineering on a roundabout project at the intersection of CR 800 E. (Kissell Rd.) and Oak St. to replace an existing traffic signal. This traffic signal was installed in 2017 as a temporary measure to assist with traffic management of the intersection until a roundabout could be designed, funded and constructed. 

Property owners directly affected by the construction have been contacted. Preliminary construction will take place in 2022 with full construction taking place in 2023. It is anticipated that this project will require a 90-day full closure of this intersection with traffic following a different route.