The tables below list the current plans for pathways that will be constructed in Zionsville. This is up-to-date as of March 1, 2009.
|
Recently completed pathways |
||||
| Name | Location | Span | Comments | |
|
1 |
Willow Road Pathway |
Willow Road |
Elm Court to 421 |
Completed in summer 2008 |
|
6b |
Turkey Foot Park Bridge |
Eagle Creek |
Turkey Foot Road to Turkey Foot Park |
Completed in fall 2008 |
|
Priority Pathways Under Construction |
||||
|
|
Name |
Location |
Span |
Comments |
|
4 |
Starkey Road Pathway |
Starkey Road |
Hickory Lane to Nancy Burton Parking Lot |
Construction begun in early 2008; completion in Spring 2009 |
|
11 |
Austin Oaks Pathway |
Willow Road |
421 to County Line |
Completed in fall 2008 except curb cuts at Willow Road and US421 intersection. Intersection is being designed to modify the signal and include pedestrian crossing signals. Must be approved by INDOT. |
|
22/23 |
Pathway on 106th Street |
106th Street |
Michigan Rd. to Zionsville Road |
Construction begins 3Q08; complete in 2009 |
|
Priority Pathways In Design/Pre-Construction Phase |
||||
|
|
Name |
Location |
Span |
Comments |
|
3 |
Eagle Creek Pathway |
Eagle Creek |
100′ Bridge to Zionsville Road |
In the process of acquiring rights-of-way |
|
6a/6c |
Turkey Foot Park to Willow Road |
Woods |
Turkey Foot Park to Willow Road |
Design in 2009; construction 2010-2011 |
|
18 |
Lion’s Park to Raintree |
334 |
Lion’s Park to Raintree Drive |
Design in 2009; right-of-way acquisition in 2010; construction 2010-2011. Projects #18 and #19 are currently being treated as one project. May be split if funding is not fully available. |
|
19 |
Raintree to 421 Pathway |
334 |
Raintree Drive to 421 |
Design in 2009; right-of-way acquisition in 2010; construction 2010-2011 |
|
|
Turkeyfoot Pathway |
Turkeyfoot Ave. |
Turkeyfoot Park to Mulberry St. |
Design in 2009; right-of-way acquisition in 2010; construction 2011 |
|
Other Priority Pathways |
||||
|
|
Name |
Location |
Span |
Comments |
|
16 |
Connect Rail Trail to 334 |
Rail Trail |
334 to Rail Trail |
|
|
|
Templin Road Pathway |
Templin Road |
Willow Rd, to Lost Run Farms pathway |
|
(As of March 19, 2004)
Pathways Longer Term Plan
There are numerous projects in the conceptual stage for Zionsvile and its outlying area. These can be seen on a larger map of the area. This map will require downloading for viewing and is about 1M in size. Map
Listed below are most of these longer term projects that have not quite made it to the 5-Year Plan.
1. Holliday Road. Map
2. Irishman Run Trail. Map
3. Austin Oaks Pathway. Map
4. Little Eagle Creek Trail. Map
5. Southwest Loop. Map
6. Turkey Foot North Pathway. Map
7. Extended Rail Trail North. Map
8. Roadways:
CR875E/Cooper Road
CR800E/Kissel Road
CR300S
CR400S
CR550S
Whitestown Road
Cruse Road
CR800S/96th Street
South Ford Road
Templin Road