Sewer Extension Project

Areas Planned for Sewer Extensions


Phase I:

  • Eaglewood Drive
  • White Oak Ct
  • Sycamore Ct
  • CR 850 E
  • Rusell Lake Dr East and West
  • Lakeview Dr
  • Karen Dr
  • Colony Ct

Phase II:

  • Sycamore Bend Subdivision
  • Deer Ridge Subdivision
  • Spring Hills Dr

Upon more detailed evaluations of Boone Ridge Dr. and Irish Hill Ln, the residents on these private drives all have frontage along Oak St. and can connect to the existing sewer at any time. No easements allowing the extension of a sewer main have been identified. The Town will work with these properties on an individual basis if and when they desire sanitary sewer connections.

Sewer Map

Timeline

All dates are subject to change. This chart will be updated regularly as new information becomes available.

For Phase I, there are six general areas included in this project. 

  1. Sycamore Ct./White Oak Ct. - HOMES MAY NOW CONNECT 
  2. Eaglewood Dr. - HOMES MAY NOW CONNECT 
  3. Lakeview Dr. HOMES MAY NOW CONNECT 
  4. Karen Dr. HOMES MAY NOW CONNECT 
  5. Russel Lake Dr. East & West HOMES MAY NOW CONNECT 
  6. Mulberry St./Colony Ct. HOMES MAY NOW CONNECT 
  7. CR 850 E (from Oak Street approximately 4,400 feet south) - HOMES MAY NOW CONNECT 
Phase I 2021 2022 2023
Design and Permitting Oct. 2021 - Feb. 2022
Oct. 2021 - Feb. 2022  
Construction Funding Approval Dec. 2021    
Bidding and Award   March 2022 - May 2022
 
Construction   Oct. 2022 - Jan. 2023

For Phase II, there are three general areas included in this project. Work will jump between these areas based on material availability. 

  1. Sycamore Bend Subdivision
  2. Deer Ridge Subdivision
  3. Spring Hills Dr.
Phase II 2021 2022 2023 2024
Design Funding Approval Dec. 2021    
     
Design and Permitting   Aug. 2022 - Feb. 2023
Aug. 2022 - Feb. 2023  
Construction Funding Approval Dec. 2021      
Bidding and Award     March 2023 - May 2023  
Construction     Aug. 2023 – Jan. 2024 Aug. 2023 – Jan. 2024