Pathways Committee
About
The Pathways Committee serves as an advisory committee to make recommendations of pathway routes and locations and policies. It also promotes the benefits of our pathway network and assists with public education and involvement in matters related to our trails. The committee is also responsible for instigating and maintaining “Bike-Friendly Community” and “Walk-Friendly Community” designations. The committee is comprised of seven members appointed by the Town Council, including one member from the Town Council. The term of service is one year. Meetings are held every other month on the second Tuesday of the month.
Members
- Kim Storen
- Jody Miller
- Brad Gressel
- Bethany Narkiewicz
- Emily Makinson
- Daniel Fowler
- Craig Melton
Agendas & Minutes
Agendas are available before the meetings. Minutes are available following approval. View the most recent agendas and minutes.
2025 Pathways Committee Report to the Town Council (on YouTube begins at 14:25)
Pathways Projects
Through the combined efforts of the Town of Zionsville DPW team members and many other organizations, several pathway projects visioned and funded by prior administrations have been and continue to be in various stages of development. Below is a list of current pathway projects currently under construction as well as potential future pathway projects.
Project Name/Location | From | To | Status | Next Step |
Oak Street Trail (Overall) | Saint Alphonsus | Blackstone Subdivision |
|
|
Phase 1 (north side) | Saint Alphonsus | Fellowship Church | Complete | |
Phase 2 (north side) | Marysville Rd. | CR 800 E | Contract being awarded. | Construction Spring 2026 |
Phase 3 (north side) | Fellowship Church | Wild Air Development | In design. | Request Town Council funding for final design and construction. |
Phase 4 (south side) | CR 800 | New Bridge over Fishback | In preliminary design. | Request Town Council funding for final design, new right of way, and construction. |
Phase 5 (south side) | Fishback Bridge | Blackstone Subdivision | In preliminary design. | Request Town Council funding for final design, new right of way, and construction. |
CR 875 E (east side) | CR 400 S. | Cobblestone Lakes Subdivision | Complete | |
North side of Whitestown Road | Cobblestone Lakes | DeRossi Subdivision | Complete | |
CR 300 S. (south side) | Appaloosa Crossings | Hamilton County Line | Contract being awarded. | Construction Spring 2026 |
Sycamore St. (north side) | S Elm St | Lions Park | Potential Construction 2027 | None |
Eagle Creek (north side) | Main St./ Zionsville Rd. | Big 4 Rail Trail | In preliminary design. | Secure construction funding. |
Special Pathway Project
Through a collaborative effort between the Town of Zionsville and the developers of Holliday Farms, a pathway is being designed along the east side of US 421/Michigan Rd. that will complete the fragmented trail system connecting the Appaloosa Crossings development to Willow Rd. It is likely that this project will be constructed in segments beginning in 2026.